El Paso Data Center Campus

Meta · El Paso · 7001 Stan Roberts Sr, El Paso, TX. Every figure below is individually sourced and dated.


Part of the tracked campus Meta / BlackRock El Paso AI Data Center Campus.

The story of El Paso Data Center Campusinherited from campus Meta / BlackRock El Paso AI Data Center Campus
Announced capex
$14B
Jobs
300 permanent reported
Derived
Cost per MW
$14M/MW
Cost per job
$47M per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterTexas(607)

The deal

Inherited from campus Meta / BlackRock El Paso AI Data Center Campus.

financier
BlackRock (managed funds) · Owns 80% of the venture; ~$4.9B cash contribution plus $12.5B debt financing
utility
El Paso Electric · Grid supplier, up to 1.0 GW (WECC region)
developer
Meta Platforms · Built the campus; retains 20% of the venture and leases capacity back (4-year initial term, up to ~20 years)
financier
Global Infrastructure Partners (GIP) · BlackRock unit; part of the 80% JV capital
financier
HPS Investment Partners · BlackRock unit; part of the JV financing

Financial structure

Inherited from campus Meta / BlackRock El Paso AI Data Center Campus.

Meta construction and development investment
$10B. Over $10B press release
Total venture development cost
$14B. Approximately $14B for buildings and infrastructure press release
BlackRock cash contribution at close
$4.9B. 80% JV interest; funded partly by $12.5B debt financing press release
Senior secured notes (Sopaipilla Investor LLC)
$12.5B. ~$12.5B of senior secured notes priced 2026-07-27 to fund the project journalist report

Investment, workforce and specs

Inherited from campus Meta / BlackRock El Paso AI Data Center Campus.

Capex
$10B source
Construction jobs
4,000 source
Permanent jobs
300 source

Power

Inherited from campus Meta / BlackRock El Paso AI Data Center Campus. Live grid demand and drought overlay only render on the campus page.

Power source
mixed
Grid operator
WECC
Interconnection

El Paso Electric grid supply, 1 GW grid interconnect, Announced. Up to 1.0 GW committed, right to request up to 1.4 GW; El Paso Electric is a WECC utility

Proposed on-site natural gas plant, 0.37 GW gas, Announced. Meta-proposed dedicated ~366 MW gas plant

Facility record

under construction

Status

hyperscale

Type

Meta

Operator

El Paso

Location

1000 MW

Critical IT

2028

Operational

On the data center map

Free to use on your site, with a link back to DEPLOY.

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q3 2026 · live Q3 2026 · 0 mo build

2018-06-23Contains modified Copernicus Sentinel data 2018
2020-05-18Contains modified Copernicus Sentinel data 2020
2022-06-02Contains modified Copernicus Sentinel data 2022
2024-09-09Contains modified Copernicus Sentinel data 2024
2025-06-08Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Meta / BlackRock El Paso AI Data Center Campus. How we source and verify it: satellite construction evidence.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • critical it mw: 1000 (claimed) · source
  • record: El Paso Data Center Campus (reported) · source
  • status: under_construction (reported) · source
  • streetAddress: 7001 Stan Roberts Sr, El Paso, TX (reported) · source · north of Stan Roberts Sr Ave, west of US-54

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Sep 2026
    Current: under construction

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is El Paso Data Center Campus?
El Paso Data Center Campus is a data center facility record on the DEPLOY registry, in El Paso. Every fact on the record is individually sourced and dated.
Who operates El Paso Data Center Campus?
Meta operates El Paso Data Center Campus, per the sourced record on the DEPLOY registry.
Is El Paso Data Center Campus operating?
El Paso Data Center Campus is recorded as under construction on the DEPLOY registry, with 1000 MW of critical IT capacity. Each figure traces to a source.
How verified is the data on El Paso Data Center Campus?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track El Paso Data Center Campus on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). El Paso Data Center Campus: data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/meta-el-paso-tx-campus