The story of Mayes County Data Center (Pryor)inherited from campus Google Pryor (MidAmerica) Data Center Campus
Announced capex
$9B
Jobs
400 permanent reported
Land owner
MidAmerica Industrial Park
Derived
Cost per job
$23M per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterOklahoma(46)

The deal

Inherited from campus Google Pryor (MidAmerica) Data Center Campus.

operator
Google · Owner and operator
land owner
MidAmerica Industrial Park · Host industrial park
utility
Grand River Dam Authority (GRDA) · Supplies power to Google's Pryor campus, including Leeward solar portfolio
grid operator
Southwest Power Pool (SPP)
developer
Leeward Renewable Energy · Solar generation developer for Google OK PPA

Financial structure

Inherited from campus Google Pryor (MidAmerica) Data Center Campus.

Google Oklahoma cloud/AI investment (2-year)
$9B. Covers Pryor expansion and a new Stillwater campus; Pryor has ~$4.4B cumulative to date press release
New OK cloud/AI investment (Pryor + Stillwater), 2 yrs
$9B. Statewide (Pryor expansion + new Stillwater campus), not Pryor-only journalist report

Investment, workforce and specs

Inherited from campus Google Pryor (MidAmerica) Data Center Campus.

Permanent jobs
400+ employed at MidAmerica campus source

Power

Inherited from campus Google Pryor (MidAmerica) Data Center Campus. Live grid demand and drought overlay only render on the campus page.

Power source
grid
Grid operator
SPP
Interconnection
Water
Evaporative cooling; the facility drew about 1.1 billion gallons of water in one year from the Neosho River via the MidAmerica Industrial Park, discharging ~253 million gallons back to the river with the remainder lost to evaporation (July 2024 to June 2025, via open-records request).

Leeward 724MW solar portfolio (via GRDA), 0.72 GW solar, Financed. Solar delivered to Grand River Dam Authority, which supplies Google's Pryor operations; part of >700MW new clean capacity added for OK ops

Facility record

operating

Status

hyperscale

Type

Google

Operator

Pryor

Location

2011

Operational

On the data center map

Free to use on your site, with a link back to DEPLOY.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • record: Mayes County Data Center (Pryor) (reported) · source
  • status: operating (reported) · source

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Sep 2026
    Current: operating

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Mayes County Data Center (Pryor)?
Mayes County Data Center (Pryor) is a data center facility record on the DEPLOY registry, in Pryor. Every fact on the record is individually sourced and dated.
Who operates Mayes County Data Center (Pryor)?
Google operates Mayes County Data Center (Pryor), per the sourced record on the DEPLOY registry.
Is Mayes County Data Center (Pryor) operating?
Mayes County Data Center (Pryor) is recorded as operating on the DEPLOY registry. Each figure traces to a source.
How verified is the data on Mayes County Data Center (Pryor)?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Mayes County Data Center (Pryor) on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Mayes County Data Center (Pryor): data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/google-mayes-county-ok

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces