Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave)

Galaxy Digital · Dickens. Every figure below is individually sourced and dated.


In clusterDickens County(6)·Texas(607)

Facility record

under construction

Status

crypto hpc

Type

Dickens

Location

260 MW

Critical IT

2027

Operational

On the data center map

Free to use on your site, with a link back to DEPLOY.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • critical it mw: Phase II 260 MW critical IT under development; 526 MW committed across Phases I-III (800 MW gross approved) (claimed) · source
  • record: Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave) (reported) · source
  • status: under_construction - Phase I (133 MW) operating Q2 2026; Phase II data hall deliveries H1 2027 (claimed) · source

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Sep 2026
    Current: under construction

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave)?
Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave) is a data center facility record on the DEPLOY registry, in Dickens. Every fact on the record is individually sourced and dated.
Who operates Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave)?
Galaxy Digital operates Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave), per the sourced record on the DEPLOY registry.
Is Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave) operating?
Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave) is recorded as under construction on the DEPLOY registry, with 260 MW of critical IT capacity. Each figure traces to a source.
How verified is the data on Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave)?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave) on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Galaxy Helios Data Center - Phase II/III Expansion (CoreWeave): data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/galaxy-helios-phase2-3-dickens-county-tx

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0