BDx CGK4 AI Data Center Park (West Java)

BDx CGK4 AI Data Center Park is an AI data center campus developed by BDx Indonesia in Jatiluhur (Purwakarta). 0.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · BDx Indonesia · PT PLN (Persero) · Jatiluhur (Purwakarta), Indonesia


Capacity: announced vs energized

Announced-to-energized gap: 0.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

BDx CGK4 AI Data Center Park (West Java) capacity claims
Source
Announced0.50 GW2024-07-31reportedjournalist report

Key facts

0.50 GW

Announced

0 GW

Energized

BDx Indonesia

Developer

Indonesia

Location

0.50 GW

Announced-to-energized gap

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

Groundbreaking (company-claimed, Sep 2026)
640 MW AI campus in Jatiluhur, West Java; 845 MVA PLN grid capacity; built over about three years.
Building 1 (company-claimed)
First of six buildings; 120 MW IT in phases; first contracted phase early 2027.
Cooling (company-claimed)
Direct-to-chip liquid cooling for up to 500 kW per rack.
Certification and power (company-claimed)
NVIDIA DGX-Ready certified Apr 2025; 5 km from Jatiluhur Dam; hydro deal with PJT planned.
Platform (company-claimed)
Part of three Indonesia AI campuses with 1.2 GVA+ grid capacity; $320M loan facility in 2026.
Backer
I Squared Capital

On the data center map

Every tracked data center is on this map, centered on BDx CGK4 AI Data Center Park. Pan or zoom out to see how close rivals are building.

Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.

Free to use on your site, with a link back to DEPLOY.

The deal

developer
BDx Indonesia · Colo host/developer (BDx / Indosat / Lintasarta JV).
operator
Lintasarta · Runs Deka GPU / GPU Merdeka here.
grid operator
PT PLN (Persero) · 30 MVA PPA across CGK3A + CGK4.
chip supplier
NVIDIA · H100 SXM (DGX-Ready).

Why here

BDx CGK4 AI Data Center Park is in Jatiluhur (Purwakarta). It connects to the PT PLN (Persero) grid. This siting summary is composed from the record's held fields, not speculation; see methodology.

Timeline

  1. Aug 2026
    party added
    chip_supplier: NVIDIA
  2. Nov 2026
    Current: Partially energized

Sources

720c5a47-de2f-4387-bf19-da401da0655e · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is BDx CGK4 AI Data Center Park (West Java)?
BDx CGK4 AI Data Center Park (West Java) is an AI data center campus tracked on the DEPLOY registry, located in Jatiluhur (Purwakarta). DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will BDx CGK4 AI Data Center Park (West Java) use?
BDx CGK4 AI Data Center Park (West Java) has 0.50 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building BDx CGK4 AI Data Center Park (West Java)?
BDx Indonesia is recorded as a party to BDx CGK4 AI Data Center Park (West Java) on the DEPLOY registry.
Is BDx CGK4 AI Data Center Park (West Java) operating yet?
As of the most recent verification on the DEPLOY registry, BDx CGK4 AI Data Center Park (West Java) is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on BDx CGK4 AI Data Center Park (West Java)?
This record has been checked against its cited sources by automated agents for the indexed registry; it has not been individually reviewed by a person. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track BDx CGK4 AI Data Center Park (West Java) on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). BDx CGK4 AI Data Center Park (West Java): AI data center campus record. Retrieved November 11, 2026, from https://registry.deploy.report/datacenters/bdx-cgk4-ai-data-center-park

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces