Data center campus
BDx CGK4 AI Data Center Park (West Java)
BDx CGK4 AI Data Center Park is an AI data center campus developed by BDx Indonesia in Jatiluhur, Purwakarta, West Java, Indonesia. 0.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · BDx Indonesia · PT PLN (Persero) · Jatiluhur, Purwakarta, West Java, Indonesia
Capacity: announced vs energized
Announced-to-energized gap: 0.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.50 GW | 2024-07-31 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
BDx Indonesia
Developer
Grid
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on BDx CGK4 AI Data Center Park. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
The deal
- developer
- BDx Indonesia · Colo host/developer (BDx / Indosat / Lintasarta JV).
- operator
- Lintasarta · Runs Deka GPU / GPU Merdeka here.
- grid operator
- PT PLN (Persero) · 30 MVA PPA across CGK3A + CGK4.
- chip supplier
- NVIDIA · H100 SXM (DGX-Ready).
Why here
BDx CGK4 AI Data Center Park is in Jatiluhur, Purwakarta, West Java, Indonesia. It connects to the PT PLN (Persero) grid. This siting summary is composed from the record's held fields, not speculation; see methodology.
Timeline
- Aug 2026party addedchip_supplier: NVIDIA
- Sep 2026Current: Partially energized
Sources
- BDx Launches First Phase of 500MW Renewable-Powered AI Campus in Indonesia · BDx Data Centers
- Lintasarta Presents GPU Merdeka, powered by NVIDIA · Lintasarta
720c5a47-de2f-4387-bf19-da401da0655e · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Common questions
What is BDx CGK4 AI Data Center Park (West Java)?
How much power will BDx CGK4 AI Data Center Park (West Java) use?
Who is building BDx CGK4 AI Data Center Park (West Java)?
Is BDx CGK4 AI Data Center Park (West Java) operating yet?
How verified is the data on BDx CGK4 AI Data Center Park (West Java)?
Deploy Watch
Track BDx CGK4 AI Data Center Park (West Java) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). BDx CGK4 AI Data Center Park (West Java): AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/bdx-cgk4-ai-data-center-park
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/bdx-cgk4-ai-data-center-park.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/bdx-cgk4-ai-data-center-park
- Data documentation: /data
- Query this programmatically: Deploy MCP