Data center campus

Alterra Marshall Technology & Energy Center

Alterra Marshall Technology & Energy Center is an AI data center campus developed by Alterra Development in Michigan, Marshall. 1.40 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Stalled · Alterra Development · greenfield · Marshall, Michigan, United States


Capacity: announced vs energized

Announced-to-energized gap: 1.40 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2027. 15 months away. Claimed by City of Marshall (source).

Alterra Marshall Technology & Energy Center capacity claims
Source
Announced1.40 GW2025-12-18reportedjournalist report

Key facts

stalled

Lifecycle

1.40 GW

Announced

0 GW

Energized

Alterra Development

Developer

1.40 GW

Announced-to-energized gap

On the data center map

Every tracked data center is on this map, centered on Alterra Marshall Technology & Energy Center. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of Alterra Marshall Technology & Energy Center
Announced capex
$1M
Jobs
300 permanent reported
Cooling
Closed-loop liquid cooling (proposed)
Grid
Frozen locally, and shrinking: Marshall has a moratorium that blocks approval of any data center until at least August 2027. The developer has since dropped the on-site gas plant that would have carried a gigawatt, cutting the projected power demand by about 60 percent.
Land owner
City of Marshall Local Development Finance Authority
Derived
Cost per MW
$800/MW
Cost per job
$4K per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterMichigan(59)

The deal

developer
Alterra Development · Toronto-based; founder James Jarvis; bought Brooks Industrial Park land from Marshall LDFA.
land owner
City of Marshall Local Development Finance Authority · Land seller; authorized sale of the 270-acre parcel Oct 30 2025.

Power

Power source
mixed
Interconnection
Frozen locally, and shrinking: Marshall has a moratorium that blocks approval of any data center until at least August 2027. The developer has since dropped the on-site gas plant that would have carried a gigawatt, cutting the projected power demand by about 60 percent.
Water
Closed-loop liquid cooling proposed to minimize water use; developer said it would not draw from Stuart Lake (reported, Dec 2025). No gpd figure sourced.

Grid import (peak), 0.40 GW grid interconnect, Announced. Up to ~400 MW grid import at peak; MISO region, supplying utility unconfirmed.

On-site natural gas turbine plant, 1 GW gas, Announced. ~1,000 MW behind-the-meter gas; air permit not yet filed.

Marshall Technology & Energy Center on-site gas plant, 1 GW gas, Cancelled. ~1,000 MW on-site natural-gas turbines originally proposed; Alterra later reportedly decided not to build the gas plant (mayor's statement, Aug 2026), cutting project energy use ~60%.

County water status: No drought in Calhoun County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

Alterra Marshall Technology & Energy Center sits on greenfield in Michigan, Marshall. It draws on mixed power, interconnection is Frozen locally, and shrinking: Marshall has a moratorium that blocks approval of any data center until at least August 2027. The developer has since dropped the on-site gas plant that would have carried a gigawatt, cutting the projected power demand by about 60 percent.. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

270-acre land purchase (Brooks Industrial Park)
$1M. LDFA-authorized sale of the 270-acre parcel; total project capex characterized only as 'billions' (no figure). journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Cooling
Closed-loop liquid cooling (proposed) source
Permanent jobs
300 to 500 skilled jobs (Alterra estimate to LDFA; no construction/permanent split) source

Timeline

  1. Aug 2026
    party added
    land_owner: City of Marshall Local Development Finance Authority
  2. Sep 2026
    Current: Stalled

Sources

f6b83182-0a0d-448e-9e52-8aed60c10086 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Alterra Marshall Technology & Energy Center?
Alterra Marshall Technology & Energy Center is an AI data center campus tracked on the DEPLOY registry, located in Marshall. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Alterra Marshall Technology & Energy Center use?
Alterra Marshall Technology & Energy Center has 1.40 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Alterra Marshall Technology & Energy Center?
Alterra Development is recorded as a party to Alterra Marshall Technology & Energy Center on the DEPLOY registry.
Is Alterra Marshall Technology & Energy Center operating yet?
As of the most recent verification on the DEPLOY registry, Alterra Marshall Technology & Energy Center is stalled. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Alterra Marshall Technology & Energy Center?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Alterra Marshall Technology & Energy Center on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Alterra Marshall Technology & Energy Center: AI data center campus record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/alterra-marshall-michigan