Data center facility
Mesa Data Center
Google · Mesa. Every figure below is individually sourced and dated.
Part of the tracked campus Google Mesa Data Center (Redhawk).
- Announced capex
- $600M
- Cooling
- Air-cooled
- Cost per MW
- $2M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterArizona(149)
The deal
Inherited from campus Google Mesa Data Center (Redhawk).
- utility
- Salt River Project (SRP)
- operator
- NextEra Energy Resources · Operator of the contracted generation, not the data center.
- operator
- offtaker
- Salt River Project · SRP procures >430 MW new carbon-free capacity from NextEra facilities to supply the Google Mesa campus (agreement announced March 18, 2024)
Financial structure
Inherited from campus Google Mesa Data Center (Redhawk).
- Redhawk Phase 1 capital outlay
- $600M. Committed spend threshold by July 2025 (Phase 1 completion deadline) journalist report
- Redhawk full campus buildout (est.)
- $1B. Full ~750,000 sq ft buildout valuation journalist report
Investment, workforce and specs
Inherited from campus Google Mesa Data Center (Redhawk).
Power
Inherited from campus Google Mesa Data Center (Redhawk). Live grid demand and drought overlay only render on the campus page.
- Power source
- solar storage
- Grid operator
- WECC
- Interconnection
- Water
- Air-cooled to minimize water consumption given regional water scarcity (Google)
SRP/NextEra carbon-free supply, 0.43 GW solar, Announced. 430+ MW of new carbon-free capacity contracted via SRP; blends wind, solar and battery storage.
Sonoran Solar Energy Center, 0.26 GW solar, Energized. 260 MW solar + 1 GWh (4-hr) battery storage; NextEra facility south of Buckeye, AZ; commissioned and operational. Part of SRP agreement supplying >430 MW carbon-free to Google Mesa
Storey Energy Center, 0.09 GW solar, Energized. 88 MW solar + battery storage; NextEra facility in Coolidge, AZ; commissioned and operational
Babbitt Ranch Energy Center, 0.16 GW wind, Under construction. 161 MW wind, NextEra facility in Coconino County (north of Flagstaff); under development. Part of SRP >430 MW carbon-free agreement
Facility record
On the data center map
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Sep 2026Current: operating
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is Mesa Data Center?
Who operates Mesa Data Center?
Is Mesa Data Center operating?
How verified is the data on Mesa Data Center?
Deploy Watch
Track Mesa Data Center on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). Mesa Data Center: data center facility record. Retrieved September 27, 2026, from https://registry.deploy.report/datacenters/facilities/google-mesa-az
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/google-mesa-az.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/google-mesa-az
- Data documentation: /data
- Query this programmatically: Deploy MCP