Prince William Digital Gateway vs STACK Stafford Technology Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Prince William Digital Gateway | STACK Stafford Technology Campus | |
|---|---|---|
| Announced capacity | 1.70 GW | 1.10 GW |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | 1.70 GW | 1.10 GW |
| Lifecycle | cancelled | permitted |
| Developer | Compass Datacenters | STACK Infrastructure |
| Location | Gainesville, Virginia, United States | Stafford, Virginia, United States |
| Grid | PJM | PJM |
| Acreage | 2,100 acres | 500 acres |
On the map
Common questions
Which is bigger, Prince William Digital Gateway or STACK Stafford Technology Campus?
By announced capacity, Prince William Digital Gateway is larger: 1.70 GW versus 1.10 GW. Announced figures are claims, not built capacity.
Which is further along, Prince William Digital Gateway or STACK Stafford Technology Campus?
Prince William Digital Gateway is cancelled; STACK Stafford Technology Campus is permitted. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Prince William Digital Gateway and STACK Stafford Technology Campus?
Prince William Digital Gateway is in Gainesville, Virginia, United States; STACK Stafford Technology Campus is in Stafford, Virginia, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.