Data center comparison
Alpha Digital Campus vs Matrix Data Center Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Alpha Digital Campus | Matrix Data Center Campus | |
|---|---|---|
| Announced capacity | 2 GW | 0.80 GW |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | 2 GW | 0.80 GW |
| Lifecycle | announced | under construction |
| Developer | PowerBridge | MSB Global Services |
| Location | Pecos, Texas, United States | Sulphur Springs, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 3,400 acres | 390 acres |
On the map
Common questions
Which is bigger, Alpha Digital Campus or Matrix Data Center Campus?
By announced capacity, Alpha Digital Campus is larger: 2 GW versus 0.80 GW. Announced figures are claims, not built capacity.
Which is further along, Alpha Digital Campus or Matrix Data Center Campus?
Alpha Digital Campus is announced; Matrix Data Center Campus is under construction. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Alpha Digital Campus and Matrix Data Center Campus?
Alpha Digital Campus is in Pecos, Texas, United States; Matrix Data Center Campus is in Sulphur Springs, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.