Data center comparison
EdgeCore Mesa vs QTS Phoenix 3 Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| EdgeCore Mesa | QTS Phoenix 3 Campus | |
|---|---|---|
| Announced capacity | 0.45 GW | 0.75 GW |
| Energized capacity | 0.21 GW | not recorded |
| Announced-to-energized gap | 0.24 GW | 0.75 GW |
| Lifecycle | permitted | permitted |
| Developer | EdgeCore Digital Infrastructure | QTS Data Centers |
| Location | Mesa, Arizona, United States | Glendale, Arizona, United States |
| Grid | WECC | WECC |
| Acreage | 84 acres | 375 acres |
On the map
Common questions
Which is bigger, EdgeCore Mesa or QTS Phoenix 3 Campus?
By announced capacity, QTS Phoenix 3 Campus is larger: 0.75 GW versus 0.45 GW. Announced figures are claims, not built capacity.
Which is further along, EdgeCore Mesa or QTS Phoenix 3 Campus?
EdgeCore Mesa is permitted; QTS Phoenix 3 Campus is permitted. Energized capacity: 0.21 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are EdgeCore Mesa and QTS Phoenix 3 Campus?
EdgeCore Mesa is in Mesa, Arizona, United States; QTS Phoenix 3 Campus is in Glendale, Arizona, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.