Data center comparison
Crusoe Childress Campus vs Lancium Fort Stockton Clean Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Crusoe Childress Campus | Lancium Fort Stockton Clean Campus | |
|---|---|---|
| Announced capacity | 1 GW | 0.33 GW |
| Energized capacity | 0 GW | 0.03 GW |
| Announced-to-energized gap | 1 GW | 0.30 GW |
| Lifecycle | announced | partially energized |
| Developer | Crusoe | Lancium |
| Location | Childress, Texas, United States | Fort Stockton, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 270 acres | 110 acres |
On the map
Common questions
Which is bigger, Crusoe Childress Campus or Lancium Fort Stockton Clean Campus?
By announced capacity, Crusoe Childress Campus is larger: 1 GW versus 0.33 GW. Announced figures are claims, not built capacity.
Which is further along, Crusoe Childress Campus or Lancium Fort Stockton Clean Campus?
Crusoe Childress Campus is announced; Lancium Fort Stockton Clean Campus is partially energized. Energized capacity: 0 GW versus 0.03 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Crusoe Childress Campus and Lancium Fort Stockton Clean Campus?
Crusoe Childress Campus is in Childress, Texas, United States; Lancium Fort Stockton Clean Campus is in Fort Stockton, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.