DEPLOY

Data center comparison

Project Blue vs QTS Phoenix 3 Campus

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Project BlueQTS Phoenix 3 Campus
Announced capacity0.60 GW0.75 GW
Energized capacitynot recordednot recorded
Announced-to-energized gap0.60 GW0.75 GW
Lifecycleunder constructionpermitted
DeveloperBeale InfrastructureQTS Data Centers
LocationTucson, Arizona, United StatesGlendale, Arizona, United States
GridWECCWECC
Acreage290 acres375 acres

On the map

Common questions

Which is bigger, Project Blue or QTS Phoenix 3 Campus?
By announced capacity, QTS Phoenix 3 Campus is larger: 0.75 GW versus 0.60 GW. Announced figures are claims, not built capacity.
Which is further along, Project Blue or QTS Phoenix 3 Campus?
Project Blue is under construction; QTS Phoenix 3 Campus is permitted. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Project Blue and QTS Phoenix 3 Campus?
Project Blue is in Tucson, Arizona, United States; QTS Phoenix 3 Campus is in Glendale, Arizona, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.