Data center comparison
Vantage Port Washington (Lighthouse) Campus vs Vantage TX1 San Antonio Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Vantage Port Washington (Lighthouse) Campus | Vantage TX1 San Antonio Campus | |
|---|---|---|
| Announced capacity | 0.90 GW | not recorded |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | 0.90 GW | not recorded |
| Lifecycle | under construction | partially energized |
| Developer | Vantage Data Centers | Vantage Data Centers |
| Location | Port Washington, Wisconsin, United States | San Antonio, Texas, United States |
| Grid | MISO | ERCOT |
| Acreage | 672 acres | not recorded |
On the map
Common questions
Which is further along, Vantage Port Washington (Lighthouse) Campus or Vantage TX1 San Antonio Campus?
Vantage Port Washington (Lighthouse) Campus is under construction; Vantage TX1 San Antonio Campus is partially energized. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Vantage Port Washington (Lighthouse) Campus and Vantage TX1 San Antonio Campus?
Vantage Port Washington (Lighthouse) Campus is in Port Washington, Wisconsin, United States; Vantage TX1 San Antonio Campus is in San Antonio, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.