| Vantage Data Centers — Frontier | Vantage TX1 San Antonio Campus | |
|---|---|---|
| Announced capacity | 1.40 GW | not recorded |
| Energized capacity | 0 GW | not recorded |
| Announced-to-energized gap | 1.40 GW | not recorded |
| Lifecycle | under construction | partially energized |
| Developer | Vantage Data Centers | Vantage Data Centers |
| Location | Albany (Shackelford County), Texas, United States | San Antonio, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | not recorded | not recorded |
On the map
Common questions
Which is further along, Vantage Data Centers — Frontier or Vantage TX1 San Antonio Campus?
Vantage Data Centers — Frontier is under construction; Vantage TX1 San Antonio Campus is partially energized. Energized capacity: 0 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Vantage Data Centers — Frontier and Vantage TX1 San Antonio Campus?
Vantage Data Centers — Frontier is in Albany (Shackelford County), Texas, United States; Vantage TX1 San Antonio Campus is in San Antonio, Texas, United States. Each record on DEPLOY is sourced and dated.