| Vantage JHB1 Johor | YTL Green Data Center Park | |
|---|---|---|
| Announced capacity | not recorded | 0.50 GW |
| Energized capacity | not recorded | 0.05 GW |
| Announced-to-energized gap | not recorded | 0.45 GW |
| Lifecycle | energized | partially energized |
| Developer | Vantage Data Centers APAC | YTL Power International / YTL Data Center Holdings |
| Location | Johor Bahru, Johor, Malaysia | Kulai, Johor, Malaysia |
| Grid | not recorded | Tenaga Nasional Berhad (TNB) |
| Acreage | not recorded | 1,640 acres |
On the map
Common questions
Which is further along, Vantage JHB1 Johor or YTL Green Data Center Park?
Vantage JHB1 Johor is energized; YTL Green Data Center Park is partially energized. Energized capacity: not recorded versus 0.05 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Vantage JHB1 Johor and YTL Green Data Center Park?
Vantage JHB1 Johor is in Johor Bahru, Johor, Malaysia; YTL Green Data Center Park is in Kulai, Johor, Malaysia. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.