Data center comparison
Stargate Lordstown vs Vantage Data Centers — Frontier
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Stargate Lordstown | Vantage Data Centers — Frontier | |
|---|---|---|
| Announced capacity | 0.30 GW | 1.40 GW |
| Energized capacity | 0 GW | 0 GW |
| Announced-to-energized gap | 0.30 GW | 1.40 GW |
| Lifecycle | announced | under construction |
| Developer | OpenAI | Vantage Data Centers |
| Location | Lordstown, Ohio, United States | Albany (Shackelford County), Texas, United States |
| Grid | PJM | ERCOT |
| Acreage | not recorded | not recorded |
On the map
Common questions
Which is bigger, Stargate Lordstown or Vantage Data Centers — Frontier?
By announced capacity, Vantage Data Centers — Frontier is larger: 1.40 GW versus 0.30 GW. Announced figures are claims, not built capacity.
Which is further along, Stargate Lordstown or Vantage Data Centers — Frontier?
Stargate Lordstown is announced; Vantage Data Centers — Frontier is under construction. Energized capacity: 0 GW versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Stargate Lordstown and Vantage Data Centers — Frontier?
Stargate Lordstown is in Lordstown, Ohio, United States; Vantage Data Centers — Frontier is in Albany (Shackelford County), Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.