Data center comparison
PORTS-Pike Technology Campus vs Vantage Data Centers — Frontier
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| PORTS-Pike Technology Campus | Vantage Data Centers — Frontier | |
|---|---|---|
| Announced capacity | 10 GW | 1.40 GW |
| Energized capacity | 0 GW | 0 GW |
| Announced-to-energized gap | 10 GW | 1.40 GW |
| Lifecycle | announced | under construction |
| Developer | SB Energy | Vantage Data Centers |
| Location | Piketon, Ohio, United States | Albany (Shackelford County), Texas, United States |
| Grid | PJM | ERCOT |
| Acreage | not recorded | not recorded |
On the map
Common questions
Which is bigger, PORTS-Pike Technology Campus or Vantage Data Centers — Frontier?
By announced capacity, PORTS-Pike Technology Campus is larger: 10 GW versus 1.40 GW. Announced figures are claims, not built capacity.
Which is further along, PORTS-Pike Technology Campus or Vantage Data Centers — Frontier?
PORTS-Pike Technology Campus is announced; Vantage Data Centers — Frontier is under construction. Energized capacity: 0 GW versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are PORTS-Pike Technology Campus and Vantage Data Centers — Frontier?
PORTS-Pike Technology Campus is in Piketon, Ohio, United States; Vantage Data Centers — Frontier is in Albany (Shackelford County), Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.