EdgeCore MesaGoogle Mesa Data Center
Announced capacity0.45 GW0.40 GW
Energized capacity0.21 GWnot recorded
Announced-to-energized gap0.24 GW0.40 GW
Lifecyclepermittedenergized
DeveloperEdgeCore Digital InfrastructureNextEra Energy Resources
LocationMesa, Arizona, United StatesMesa, Arizona, United States
GridWECCWECC
Acreage84 acres185 acres

On the map

Common questions

Which is bigger, EdgeCore Mesa or Google Mesa Data Center?
By announced capacity, EdgeCore Mesa is larger: 0.45 GW versus 0.40 GW. Announced figures are claims, not built capacity.
Which is further along, EdgeCore Mesa or Google Mesa Data Center?
EdgeCore Mesa is permitted; Google Mesa Data Center is energized. Energized capacity: 0.21 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are EdgeCore Mesa and Google Mesa Data Center?
EdgeCore Mesa is in Mesa, Arizona, United States; Google Mesa Data Center is in Mesa, Arizona, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.