Crusoe Stargate Site 2 vs Stargate Abilene

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Crusoe Stargate Site 2Stargate Abilene
Announced capacitynot recorded1.20 GW
Energized capacitynot recorded0.30 GW
Announced-to-energized gapnot recorded0.90 GW
Lifecycleunder constructionpartially energized
DeveloperCrusoeOpenAI
LocationAlbany (Shackelford County), Texas, United StatesAbilene, Texas, United States
GridERCOTERCOT
Acreagenot recorded875 acres

On the map

Common questions

Which is further along, Crusoe Stargate Site 2 or Stargate Abilene?
Crusoe Stargate Site 2 is under construction; Stargate Abilene is partially energized. Energized capacity: not recorded versus 0.30 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Crusoe Stargate Site 2 and Stargate Abilene?
Crusoe Stargate Site 2 is in Albany (Shackelford County), Texas, United States; Stargate Abilene is in Abilene, Texas, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.