Data center comparison
Crusoe Abilene AI Data Center vs Stargate Abilene
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Crusoe Abilene AI Data Center | Stargate Abilene | |
|---|---|---|
| Announced capacity | not recorded | 1.20 GW |
| Energized capacity | not recorded | 0.30 GW |
| Announced-to-energized gap | not recorded | 0.90 GW |
| Lifecycle | partially energized | partially energized |
| Developer | Crusoe | OpenAI |
| Location | Abilene, Texas, United States | Abilene, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | not recorded | 875 acres |
On the map
Common questions
Which is further along, Crusoe Abilene AI Data Center or Stargate Abilene?
Crusoe Abilene AI Data Center is partially energized; Stargate Abilene is partially energized. Energized capacity: not recorded versus 0.30 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Crusoe Abilene AI Data Center and Stargate Abilene?
Crusoe Abilene AI Data Center is in Abilene, Texas, United States; Stargate Abilene is in Abilene, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.