Data center comparison
Galaxy Helios Campus vs GW Ranch
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Galaxy Helios Campus | GW Ranch | |
|---|---|---|
| Announced capacity | 1.60 GW | 1 GW |
| Energized capacity | 0.13 GW | not recorded |
| Announced-to-energized gap | 1.47 GW | 1 GW |
| Lifecycle | partially energized | permitted |
| Developer | Galaxy Digital | Pacifico Energy |
| Location | Afton, Texas, United States | Fort Stockton, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 2,200 acres | 8,000 acres |
On the map
Common questions
Which is bigger, Galaxy Helios Campus or GW Ranch?
By announced capacity, Galaxy Helios Campus is larger: 1.60 GW versus 1 GW. Announced figures are claims, not built capacity.
Which is further along, Galaxy Helios Campus or GW Ranch?
Galaxy Helios Campus is partially energized; GW Ranch is permitted. Energized capacity: 0.13 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Galaxy Helios Campus and GW Ranch?
Galaxy Helios Campus is in Afton, Texas, United States; GW Ranch is in Fort Stockton, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.