Data center comparison
Galaxy Helios Campus vs Matrix Data Center Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Galaxy Helios Campus | Matrix Data Center Campus | |
|---|---|---|
| Announced capacity | 1.60 GW | 0.80 GW |
| Energized capacity | 0.13 GW | not recorded |
| Announced-to-energized gap | 1.47 GW | 0.80 GW |
| Lifecycle | partially energized | under construction |
| Developer | Galaxy Digital | MSB Global Services |
| Location | Afton, Texas, United States | Sulphur Springs, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 2,200 acres | 390 acres |
On the map
Common questions
Which is bigger, Galaxy Helios Campus or Matrix Data Center Campus?
By announced capacity, Galaxy Helios Campus is larger: 1.60 GW versus 0.80 GW. Announced figures are claims, not built capacity.
Which is further along, Galaxy Helios Campus or Matrix Data Center Campus?
Galaxy Helios Campus is partially energized; Matrix Data Center Campus is under construction. Energized capacity: 0.13 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Galaxy Helios Campus and Matrix Data Center Campus?
Galaxy Helios Campus is in Afton, Texas, United States; Matrix Data Center Campus is in Sulphur Springs, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.