Data center comparison
Garden City Data Center vs Polaris Forge 2
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Garden City Data Center | Polaris Forge 2 | |
|---|---|---|
| Announced capacity | not recorded | 0.28 GW |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | not recorded | 0.28 GW |
| Lifecycle | energized | under construction |
| Developer | Applied Digital | Applied Digital |
| Location | Garden City, Glasscock County, Texas, United States | Harwood, North Dakota, United States |
| Grid | not recorded | MISO |
| Acreage | not recorded | 900 acres |
On the map
Common questions
Which is further along, Garden City Data Center or Polaris Forge 2?
Garden City Data Center is energized; Polaris Forge 2 is under construction. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Garden City Data Center and Polaris Forge 2?
Garden City Data Center is in Garden City, Glasscock County, Texas, United States; Polaris Forge 2 is in Harwood, North Dakota, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.