Amazon (AWS) Hermiston / Umatilla Data Center Campus vs Amazon Project Rainier Data Center

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Amazon (AWS) Hermiston / Umatilla Data Center CampusAmazon Project Rainier Data Center
Announced capacity0.50 GW2.20 GW
Energized capacity0.10 GW0.91 GW
Announced-to-energized gap0.40 GW1.29 GW
Lifecyclepartially energizedpartially energized
DeveloperAmazonAnthropic
LocationHermiston, Oregon, United StatesNew Carlisle, Indiana, United States
GridWECCPJM
Acreage810 acresnot recorded

On the map

Common questions

Which is bigger, Amazon (AWS) Hermiston / Umatilla Data Center Campus or Amazon Project Rainier Data Center?
By announced capacity, Amazon Project Rainier Data Center is larger: 2.20 GW versus 0.50 GW. Announced figures are claims, not built capacity.
Which is further along, Amazon (AWS) Hermiston / Umatilla Data Center Campus or Amazon Project Rainier Data Center?
Amazon (AWS) Hermiston / Umatilla Data Center Campus is partially energized; Amazon Project Rainier Data Center is partially energized. Energized capacity: 0.10 GW versus 0.91 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Amazon (AWS) Hermiston / Umatilla Data Center Campus and Amazon Project Rainier Data Center?
Amazon (AWS) Hermiston / Umatilla Data Center Campus is in Hermiston, Oregon, United States; Amazon Project Rainier Data Center is in New Carlisle, Indiana, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.