| Meta Beaver Dam Data Center | Meta Los Lunas Data Center Campus | |
|---|---|---|
| Announced capacity | 0.22 GW | not recorded |
| Energized capacity | not recorded | 0.04 GW |
| Announced-to-energized gap | 0.22 GW | not recorded |
| Lifecycle | under construction | partially energized |
| Developer | Meta | Meta |
| Location | Beaver Dam, Wisconsin, United States | Los Lunas, Valencia County, New Mexico, United States |
| Grid | MISO | WECC |
| Acreage | not recorded | 750 acres |
On the map
Common questions
Which is further along, Meta Beaver Dam Data Center or Meta Los Lunas Data Center Campus?
Meta Beaver Dam Data Center is under construction; Meta Los Lunas Data Center Campus is partially energized. Energized capacity: not recorded versus 0.04 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Meta Beaver Dam Data Center and Meta Los Lunas Data Center Campus?
Meta Beaver Dam Data Center is in Beaver Dam, Wisconsin, United States; Meta Los Lunas Data Center Campus is in Los Lunas, Valencia County, New Mexico, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.