Data center comparison
Galaxy Helios Campus vs US West LAS1
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Galaxy Helios Campus | US West LAS1 | |
|---|---|---|
| Announced capacity | 1.60 GW | not recorded |
| Energized capacity | 0.13 GW | not recorded |
| Announced-to-energized gap | 1.47 GW | not recorded |
| Lifecycle | partially energized | energized |
| Developer | Galaxy Digital | CoreWeave |
| Location | Afton, Texas, United States | Las Vegas, Nevada, USA |
| Grid | ERCOT | not recorded |
| Acreage | 2,200 acres | not recorded |
On the map
Common questions
Which is further along, Galaxy Helios Campus or US West LAS1?
Galaxy Helios Campus is partially energized; US West LAS1 is energized. Energized capacity: 0.13 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Galaxy Helios Campus and US West LAS1?
Galaxy Helios Campus is in Afton, Texas, United States; US West LAS1 is in Las Vegas, Nevada, USA. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.