{"id":"3ba39da0-2226-4e26-b5c6-9299214fd403","slug":"nebius-vineland-new-jersey","name":"Nebius Vineland AI Data Center","aliases":["Nebius New Jersey","Vineland NJ AI factory"],"locationId":"408bea1d-4b69-4c45-aa0a-6eca84e35b06","lat":null,"lng":null,"locationPrecision":null,"landStatus":"private","lifecycleState":"partially_energized","powerSourceMix":"behind_the_meter_gas","interconnectionQueueStatus":null,"interconnectionQueueId":null,"expectedEnergizationDate":null,"dedicatedSubstation":null,"gridOperator":"PJM","waterSourceNotes":null,"servingUtility":null,"acreage":null,"totalBuildingSqft":null,"streetAddress":null,"notes":"Nebius build-to-suit GPU campus in Cumberland County with up to 300 MW planned; first phase energized late 2025 and dedicated to Microsoft under a multi-year GPU capacity agreement. Powered largely behind-the-meter (Bloom Energy fuel cells plus on-site gas engines) to bypass the PJM interconnection queue. The FY2025 20-F confirms the Vineland site and Microsoft offtake but does not state per-site MW; exact energized MW not disclosed.","keyFacts":[{"label":"NJDEP air penalty (Sep 2026)","value":"DataOne assessed $1,072,000 for running 62 Caterpillar natural-gas generators without air permits."},{"label":"Permit window (reported, Sep 2026)","value":"Generators may keep running while DataOne has 45 days to get permits; DataOne plans to move to fuel cells."},{"label":"Clean Air Act suit notice (filed, Oct 2026)","value":"Sustain SJ, represented by Earthjustice, sent an Oct 21 2026 notice of intent to sue over 62 gas generators at Vineland run without federal air permits. No lawsuit filed yet."}],"reviewStatus":"reviewed","sources":[{"url":"https://www.sec.gov/Archives/edgar/data/0001513845/000110465926052948/nbis-20251231x20f.htm","title":"Nebius Group N.V. Form 20-F FY2025"},{"url":"https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey","title":"Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey"},{"url":"https://dep.nj.gov/wp-content/uploads/newsrel/2026/dataone75894-aonocapa.pdf","title":"NJDEP Administrative Order and Notice of Civil Administrative Penalty Assessment: DATAONE Vineland (EA ID PEA260001-75894)","sourceName":"NJDEP"},{"url":"https://www.insidernj.com/sherrill-administration-issues-1-million-fine-to-vineland-data-center/","title":"Sherrill Administration Issues $1 Million Fine to Vineland Data Center","sourceName":"Insider NJ"},{"url":"https://www.nj.gov/governor/news/2026/20260922a.shtml","title":"Governor Sherrill Statement on $1.07 Million Fine Against Vineland Data Center","sourceName":"Office of the Governor of New Jersey","publishedAt":"2026-09-22"},{"url":"https://floodlightnews.org/new-jersey-dataones-illegal-still-running/","title":"New Jersey says DataOne's 62 generators are illegal. It's letting them run for 45 more days.","sourceName":"Floodlight","publishedAt":"2026-09-23"},{"url":"https://www.techradar.com/pro/new-jersey-hits-data-center-powering-microsoft-copilot-with-usd1m-fine-after-drone-expose-62-secretly-installed-gas-generators","title":"New Jersey hits data center powering Microsoft Copilot with $1M fine after drone expose","sourceName":"TechRadar Pro","publishedAt":"2026-09-23"},{"url":"https://earthjustice.org/wp-content/uploads/2026/10/2026-10-21-sustain-sj-notice-of-intent-to-sue-dataone-for-clean-air-act-violations.pdf","title":"Sustain SJ notice of intent to sue DataOne for Clean Air Act violations","sourceName":"Earthjustice","publishedAt":"2026-10-21"},{"url":"https://earthjustice.org/press/2026/community-advocates-plan-to-sue-data-center-company-over-illegal-air-pollution-in-new-jersey","title":"Community Advocates Plan to Sue Data Center Company Over Illegal Air Pollution in New Jersey","sourceName":"Earthjustice","publishedAt":"2026-10-21"}],"reviewNote":null,"createdAt":"2026-08-17T20:22:45.534Z","updatedAt":"2026-10-26T01:59:54.592Z","location":{"id":"408bea1d-4b69-4c45-aa0a-6eca84e35b06","name":"Vineland","slug":"vineland-new-jersey","kind":"city","parentLocationId":"fda583b9-b212-4f2d-8e39-021169fe9c80","region":"New Jersey","lat":39.4862777,"lng":-75.0254256,"reviewStatus":"reviewed","aliases":["Vineland, New Jersey, USA"],"collisionRisk":"high","reviewNote":null,"createdAt":"2026-08-17T20:22:45.156Z","updatedAt":"2026-11-02T18:32:15.604Z"},"parties":[{"id":"019ecbe2-3557-485b-9f9d-3d64bfb19734","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","companyId":null,"externalName":"Nebius Group N.V.","role":"operator","structureNotes":"Ticker NBIS; build-to-suit model","createdAt":"2026-08-17T20:22:47.133Z","company":null},{"id":"52e1b1cb-6ab9-42b7-8844-0cfee43c30f7","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","companyId":null,"externalName":"Microsoft","role":"offtaker","structureNotes":"Multi-year GPU capacity agreement, up to ~$17.4B total contract value through 2031 per 20-F","createdAt":"2026-08-17T20:22:47.903Z","company":null},{"id":"37f62247-23e6-4d80-8578-e9014b9695f5","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","companyId":null,"externalName":"NVIDIA","role":"chip_supplier","structureNotes":"Blackwell GPUs","createdAt":"2026-08-17T20:22:48.664Z","company":null},{"id":"6e0fb1ee-7954-41d1-aab8-149c0c1a5ef1","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","companyId":null,"externalName":"DataOne","role":"developer","structureNotes":"Build-to-suit developer of the Vineland facility (branded 'DataOne: Vineland, NJ'); first phase built in ~20 weeks in 2025","createdAt":"2026-08-19T00:29:03.478Z","company":null},{"id":"cb6a5f40-da96-4a2c-8677-904ae6ff2aac","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","companyId":null,"externalName":"Bloom Energy","role":"utility","structureNotes":"On-site solid oxide fuel-cell power provider; 10-year master agreement up to $2.6B, 328 MW installed / ~250 MW guaranteed, targeted online 2026","createdAt":"2026-08-19T00:29:04.645Z","company":null}],"capacityClaims":[{"id":"34958e6c-742e-4821-9d2e-352c81e63ee0","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","series":"announced","valueGw":0.3,"asOf":"2025-09-01T00:00:00.000Z","sourceUrl":"https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey","sourceType":"press_release","evidenceTier":"claimed","supersedesId":null,"note":"Up to 300 MW planned per company; 20-F confirms site + Microsoft offtake but not per-site MW","createdAt":"2026-08-17T20:22:46.219Z"}],"financialClaims":[],"metricClaims":[{"id":"c72be81f-4c0c-433f-9a21-976f0bcb2a54","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","metricType":"capex_usd","valueNumeric":null,"valueText":"Microsoft multi-year GPU capacity agreement valued at ~$17.4B over 5 years (expandable to ~$19.4B); Vineland is the initial delivery site","unit":null,"grantingJurisdiction":null,"asOf":"2025-06-01T00:00:00.000Z","sourceUrl":"https://convergedigest.com/nebius-inks-17-4b-deal-with-microsoft-for-ai-infrastructure/","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":null,"createdAt":"2026-08-19T00:29:02.709Z"}],"powerProjects":[{"id":"8a7bbb4b-2ba3-4fd7-aa7a-668e7ed64eea","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","name":"Vineland on-site Bloom Energy fuel cells / gas engines","type":"gas","capacityGw":null,"lifecycleState":"under_construction","sourceUrl":"https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey","evidenceTier":"claimed","note":"Behind-the-meter generation; exact MW not disclosed","createdAt":"2026-08-17T20:22:46.754Z"},{"id":"fd68c54c-b402-4cf6-a140-e69843b1e5a8","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","name":"Bloom Energy solid oxide fuel cells (Nebius US master agreement)","type":"gas","capacityGw":0.328,"lifecycleState":"under_construction","sourceUrl":"https://nebius.com/newsroom/nebius-and-bloom-energy-partner-to-power-ai-infrastructure-build-out","evidenceTier":"reported","note":"328 MW installed / ~250 MW guaranteed of on-site behind-the-meter solid oxide fuel cells (natural gas / on-site LNG), targeted online in 2026 under a 10-year master agreement worth up to $2.6B; Vineland is Nebius's first US deployment","createdAt":"2026-08-19T00:29:02.304Z"}],"facilities":[],"incidents":[],"events":[{"id":"eb50459f-2e97-4436-b27a-9484c7a8527d","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"utility: Bloom Energy","occurredAt":"2026-08-19T00:29:05.056Z","createdAt":"2026-08-19T00:29:05.056Z"},{"id":"db7d00f4-a45a-4bd9-8e3e-eb9d92cc2f8a","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: DataOne","occurredAt":"2026-08-19T00:29:03.872Z","createdAt":"2026-08-19T00:29:03.872Z"},{"id":"adc71b21-4f8f-4f51-a17d-1f3b43021d39","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"chip_supplier: NVIDIA","occurredAt":"2026-08-17T20:22:49.046Z","createdAt":"2026-08-17T20:22:49.046Z"},{"id":"f6df198f-164c-415e-a7cc-29ae17f6cf67","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"offtaker: Microsoft","occurredAt":"2026-08-17T20:22:48.285Z","createdAt":"2026-08-17T20:22:48.285Z"},{"id":"452732b2-74aa-44d9-88cc-141176522ee1","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"operator: Nebius Group N.V.","occurredAt":"2026-08-17T20:22:47.517Z","createdAt":"2026-08-17T20:22:47.517Z"},{"id":"e2ad8ed2-d5a2-49fd-a888-e84cd779ddd2","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"capacity_changed","series":"announced","oldValue":null,"newValue":"0.3","claimId":"34958e6c-742e-4821-9d2e-352c81e63ee0","detail":null,"occurredAt":"2026-08-17T20:22:46.527Z","createdAt":"2026-08-17T20:22:46.527Z"},{"id":"b9ec5bc5-c440-4a57-b03e-e6f183b7f7b3","dataCenterId":"3ba39da0-2226-4e26-b5c6-9299214fd403","eventType":"claim_recorded","series":"announced","oldValue":null,"newValue":"0.3","claimId":"34958e6c-742e-4821-9d2e-352c81e63ee0","detail":"claimed · press_release","occurredAt":"2026-08-17T20:22:46.374Z","createdAt":"2026-08-17T20:22:46.374Z"}],"capacity_picture":{"announced_gw":0.3,"contracted_gw":null,"under_construction_gw":null,"energized_gw":null,"announced_minus_energized_gw":0.3,"by_series":{"announced":{"valueGw":0.3,"asOf":"2025-09-01T00:00:00.000Z","evidenceTier":"claimed","sourceUrl":"https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey"},"contracted":null,"under_construction":null,"energized":null}},"jsonLd":{"@context":"https://schema.org","@type":"Place","name":"Nebius Vineland AI Data Center","url":"https://registry.deploy.report/datacenters/nebius-vineland-new-jersey","address":{"@type":"PostalAddress","addressLocality":"Vineland"}}}