# Nebius Vineland AI Data Center

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** 3ba39da0-2226-4e26-b5c6-9299214fd403
- **Type:** AI data center campus
- **Location:** Vineland, New Jersey, United States
- **Lifecycle state:** partially_energized
- **Announced capacity (GW):** 0.3

## Capacity ledger (append-only, dated, sourced)

- announced: 0.3 GW · claimed · as of 2025-09-01 · https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey

## Parties


## Common questions


**What is Nebius Vineland AI Data Center?**

Nebius Vineland AI Data Center is an AI data center campus tracked on the DEPLOY registry, located in Vineland. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Nebius Vineland AI Data Center use?**

Nebius Vineland AI Data Center has 0.30 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.

**Is Nebius Vineland AI Data Center operating yet?**

As of the most recent verification on the DEPLOY registry, Nebius Vineland AI Data Center is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Nebius Vineland AI Data Center?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- Nebius Group N.V. Form 20-F FY2025: https://www.sec.gov/Archives/edgar/data/0001513845/000110465926052948/nbis-20251231x20f.htm
- Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey: https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey
- NJDEP Administrative Order and Notice of Civil Administrative Penalty Assessment: DATAONE Vineland (EA ID PEA260001-75894): https://dep.nj.gov/wp-content/uploads/newsrel/2026/dataone75894-aonocapa.pdf
- Sherrill Administration Issues $1 Million Fine to Vineland Data Center: https://www.insidernj.com/sherrill-administration-issues-1-million-fine-to-vineland-data-center/
- Governor Sherrill Statement on $1.07 Million Fine Against Vineland Data Center: https://www.nj.gov/governor/news/2026/20260922a.shtml
- New Jersey says DataOne's 62 generators are illegal. It's letting them run for 45 more days.: https://floodlightnews.org/new-jersey-dataones-illegal-still-running/
- New Jersey hits data center powering Microsoft Copilot with $1M fine after drone expose: https://www.techradar.com/pro/new-jersey-hits-data-center-powering-microsoft-copilot-with-usd1m-fine-after-drone-expose-62-secretly-installed-gas-generators

Canonical: https://registry.deploy.report/datacenters/nebius-vineland-new-jersey
JSON: https://registry.deploy.report/v1/datacenters/nebius-vineland-new-jersey