# Nebius Independence AI Factory Campus

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** 6e1eef61-b5b6-431c-82d3-ff9a9c9bfa29
- **Type:** AI data center campus
- **Location:** Independence, Missouri, United States
- **Lifecycle state:** under_construction
- **Announced capacity (GW):** 1.2

## Capacity ledger (append-only, dated, sourced)

- announced: 1.2 GW · reported · as of 2026-03-04 · https://www.datacenterdynamics.com/en/news/nebius-breaks-ground-on-400-acre-data-center-campus-in-independence-missouri/
- under_construction: 0.25 GW · reported · as of 2027-06-01 · https://www.govtech.com/artificial-intelligence/independence-mo-to-reopen-old-power-plant-for-ai-data-center

## Parties

- NVIDIA (chip_supplier): https://registry.deploy.report/companies/nvidia

## Common questions


**What is Nebius Independence AI Factory Campus?**

Nebius Independence AI Factory Campus is an AI data center campus tracked on the DEPLOY registry, located in Independence. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Nebius Independence AI Factory Campus use?**

Nebius Independence AI Factory Campus has 1.20 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.

**Is Nebius Independence AI Factory Campus operating yet?**

As of the most recent verification on the DEPLOY registry, Nebius Independence AI Factory Campus is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Nebius Independence AI Factory Campus?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- Nebius Group N.V. Form 20-F FY2025: https://www.sec.gov/Archives/edgar/data/0001513845/000110465926052948/nbis-20251231x20f.htm
- Nebius breaks ground on 400-acre data center campus in Independence, Missouri: https://www.datacenterdynamics.com/en/news/nebius-breaks-ground-on-400-acre-data-center-campus-in-independence-missouri/
- Nebius Data Center FAQs: https://www.independencemo.gov/data-center-faqs

Canonical: https://registry.deploy.report/datacenters/nebius-independence-missouri
JSON: https://registry.deploy.report/v1/datacenters/nebius-independence-missouri