# Galaxy Helios Campus (CoreWeave)

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** 1c196dd2-f3bb-4512-ac6e-1fd594ad982e
- **Type:** AI data center campus
- **Location:** Afton, Texas, United States
- **Lifecycle state:** partially_energized
- **Announced capacity (GW):** 1.6
- **Energized capacity (GW):** 0.133
- **Announced-to-energized gap (GW):** 1.467

## Capacity ledger (append-only, dated, sourced)

- announced: 1.63 GW · reported · as of 2026-07-01 · https://www.prnewswire.com/news-releases/galaxy-completes-phase-i-of-its-helios-data-center-campus-delivering-133-megawatts-of-critical-it-load-to-coreweave-302818664.html
- announced: 1.6 GW · verified · as of 2026-01-31 · https://www.prnewswire.com/news-releases/galaxy-completes-ercot-interconnection-studies-and-secures-approval-for-additional-830-megawatts-at-helios-data-center-campus-doubling-total-approved-power-capacity-to-over-1-6-gigawatts-302662509.html
- contracted: 0.8 GW · reported · as of 2026-05-31 · https://www.prnewswire.com/news-releases/galaxy-completes-phase-i-of-its-helios-data-center-campus-delivering-133-megawatts-of-critical-it-load-to-coreweave-302818664.html
- energized: 0.133 GW · reported · as of 2026-05-31 · https://www.prnewswire.com/news-releases/galaxy-completes-phase-i-of-its-helios-data-center-campus-delivering-133-megawatts-of-critical-it-load-to-coreweave-302818664.html
- under_construction: 0.26 GW · reported · as of 2027-06-01 · https://www.prnewswire.com/news-releases/galaxy-completes-phase-i-of-its-helios-data-center-campus-delivering-133-megawatts-of-critical-it-load-to-coreweave-302818664.html

## Parties

- Galaxy Digital (developer): https://registry.deploy.report/companies/galaxy-digital
- CoreWeave (tenant): https://registry.deploy.report/companies/coreweave

## Common questions


**What is Galaxy Helios Campus (CoreWeave)?**

Galaxy Helios Campus (CoreWeave) is an AI data center campus tracked on the DEPLOY registry, located in Afton. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Galaxy Helios Campus (CoreWeave) use?**

Galaxy Helios Campus (CoreWeave) has 1.60 GW of announced capacity on the DEPLOY registry, of which 0.13 GW is recorded as energized, an announced-to-energized gap of 1.47 GW. Each figure is individually dated and sourced.

**Is Galaxy Helios Campus (CoreWeave) operating yet?**

As of the most recent verification on the DEPLOY registry, Galaxy Helios Campus (CoreWeave) is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Galaxy Helios Campus (CoreWeave)?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- Galaxy Completes ERCOT Interconnection Studies and Secures Approval for Additional 830 MW at Helios, Doubling Total to over 1.6 GW: https://www.prnewswire.com/news-releases/galaxy-completes-ercot-interconnection-studies-and-secures-approval-for-additional-830-megawatts-at-helios-data-center-campus-doubling-total-approved-power-capacity-to-over-1-6-gigawatts-302662509.html
- Galaxy Completes Phase I of Helios, Delivering 133 MW of Critical IT Load to CoreWeave: https://www.prnewswire.com/news-releases/galaxy-completes-phase-i-of-its-helios-data-center-campus-delivering-133-megawatts-of-critical-it-load-to-coreweave-302818664.html
- Galaxy Digital closes $1.4bn debt facility for Helios data center campus in Texas: https://www.datacenterdynamics.com/en/news/galaxy-digital-closes-14bn-debt-facility-for-helios-data-center-campus-in-texas/
- $3.5B Permits Filed for Galaxy Helios Data Center Phase 2: https://www.everythinglubbock.com/news/local-news/massive-3-5-billion-expansion-planned-at-ai-data-center-in-dickens-county/
- Galaxy's 500-Acre Texas AI Campus Reflects New Grid Model: https://www.datacenterknowledge.com/data-center-construction/galaxy-s-500-acre-texas-ai-campus-reflects-new-grid-model
- Helios facility: https://www.gem.wiki/Helios_facility